For the installation of an earth rod or electrode into a trench the following procedure is recommended.

1 Dig a trench at the required earth strip or electrode location of 200-300mm (8-12 inches) wide. The depth of the trench (typically 600mm) should be determined by the earthing system designer.

2 Cover the bottom of the trench with a stiff mix of Bentonite compound 25-50mm (1-2 inches) thick. Lay the earth strip into the trench. Ensure that the copper strip electrode is not depressed too far into the Bentonite.

3 Apply another layer of Bentonite 25-50mm (1-2 inches) thick. Ensure that the strip electrode is fully covered.

4 Carefully backfill and compact the remainder of the trench.